2026 Unit Prices for Demolition, Abatement and Site Work

Prices reviewed October 2026, next review January 2027 · Same price in Orange, Los Angeles, Riverside, San Bernardino, San Diego and Ventura counties

Every unit price from our 2026 cost guides on one page, for architects, engineers, general contractors and owners putting a budget together. Download it as a PDF or a spreadsheet below, or print this page; the tables are laid out to print cleanly. Each heading links to the full cost guide, with what’s included, examples and questions.

Download the price sheet (PDF)Download all prices (CSV for Excel)

Estimates for budgeting only, not an offer, bid or quote. Permits, government fees and testing are extra unless listed; your signed written proposal sets the price.

Demolition

ItemPriceUnitIncludes
Collapse and remove: house, garage, ADU or shed (slab left)$26.50 – $31.50per square foot of floor areaCollapse, sort, load, haul, disposal; slab stays
Full demolition to dirt (structure, foundation, slab out)$42 – $51per square foot of floor areaPlus foundation and slab break-out
Interior demolition and gut-outs, homes$22.50 – $26.50per square footNon-structural strip-out, haul-off
Fire-damaged structure demolition (slab left)$29 – $35per square footCollapse, debris and ash haul-off, slab left
Flooring removal, no asbestos$5.25 – $6.50per square footRemoval, scrape, haul-off
Self-leveler grinding, up to 1/4 in., no asbestos$5 – $6.50per square footDust-controlled grinding, cleanup, haul-off
Self-leveler or topping break-out, over 1/4 in., no asbestos$7.50 – $10.50per square footChipping, loading, hauling, disposal

Pool, wall and fence removal

ItemPriceUnitIncludes
In-ground pool removal (partial removal and backfill, or full removal)$15,750 – $31,500per poolMethod your city requires: break out the top and backfill with compaction, or remove the whole shell; drain, haul, backfill; gas, water and electrical lines to the pool capped (by licensed trades where required)
Block wall demolition, 6 ft high with footing$170 – $205per linear footWall and footing removal, haul-off
Fence removal, chain link or wood, up to 6 ft$12.25 – $14.75per linear footRemove posts and fabric, haul-off
Curb and gutter removal$20 – $25.50per linear footSaw cut, break-up, haul, recycling
Pavement striping removal, 4 in. stripe$6 – $7per linear footGrind or blast stripe off

Concrete cutting and coring

ItemPriceUnitIncludes
Core drilling, 2-inch hole, concrete up to 4 in. thick$105 – $130per holeDrilling, core removal and slurry cleanup
Core drilling, 4-inch hole, concrete up to 4 in. thick$200 – $245per holeDrilling, core removal and slurry cleanup
Core drilling, 4-inch hole, concrete 4 to 6 in. thick$225 – $275per holeDrilling, core removal and slurry cleanup
Saw cutting, plain concrete slab or paving, up to 4 in. deep$5.75 – $7.25per linear foot
Saw cutting, slab with wire mesh, up to 4 in. deep$7.50 – $9.25per linear foot
Saw cutting, slab with rebar, up to 4 in. deep$12 – $14.75per linear foot
Saw cutting, plain concrete wall, up to 4 in. deep$23 – $27.50per linear foot
Opening in a 4-inch reinforced slab on grade, under 24 SF$105 – $130per square foot
Opening in a 6-inch reinforced concrete wall, under 24 SF$140 – $170per square foot

Concrete and asphalt removal

ItemPriceUnitIncludes
Concrete slab removal, 4 in., under 5,000 SF$8.75 – $10.50per square footBreak-up, load, haul, recycling
Concrete slab removal, 4 in., 5,000 SF and up$6 – $7.25per square footBreak-up, load, haul, recycling
Concrete slab removal, 6 in., under 5,000 SF$10.50 – $13.25per square footBreak-up, load, haul, recycling
Concrete slab removal, 6 in., 5,000 SF and up$7.25 – $8.75per square footBreak-up, load, haul, recycling
Concrete slab removal, 8 in., under 5,000 SF$15.75 – $19per square footBreak-up, load, haul, recycling
Concrete slab removal, 8 in., 5,000 SF and up$10.50 – $12.75per square footBreak-up, load, haul, recycling
Asphalt removal, 4 in., under 5,000 SF$7.25 – $8.50per square footBreak-up, load, haul, recycling
Asphalt removal, 4 in., 5,000 SF and up$3.70 – $4.75per square footBreak-up, load, haul, recycling
Asphalt removal, 6 in., under 5,000 SF$8 – $9.25per square footBreak-up, load, haul, recycling
Asphalt removal, 6 in., 5,000 SF and up$4.50 – $5.75per square footBreak-up, load, haul, recycling
Concrete and asphalt crushing to base, on site$7.50 – $11.25per tonCrusher mobilization, crushing, stockpiling

A job just under 5,000 SF is never billed more than the same job at 5,000 SF.

Excavation and grading

ItemPriceUnitIncludes
Excavation and soil export$94 – $115per cubic yardDig, load, haul, clean-dirt disposal
Rough grading, on-site cut and fill$1.35 – $1.85per square foot of padMachine cut, fill and shape
Fine grading$1.10per square footGrader finish to plan grades
Fill dirt, delivered, placed and compacted$62 – $77per cubic yardFill material delivered, spread, compacted
Trenching by machine, 2 ft wide x 4 ft deep, backfilled and compacted$11.75 – $14per linear footExcavate, backfill, compact; spoils spread on site
Base rock (crushed aggregate base), 6 in., placed$3.15 – $3.95per square footBase delivered, spread, compacted
Lime stabilization (lime-treated subgrade), 6 in.$2.40 – $3.15per square footLime, mixing, compaction
Utility potholing by hand (up to 1 cubic yard)$400 – $490eachHand dig to expose, backfill

Land clearing

ItemPriceUnitIncludes
Lot clearing and grubbing (brush, trees under 6 in.)$22,000 – $26,250per acreCut, grub, chip, haul-off
Heavy clearing and grubbing (trees up to 16 in.)$35,750 – $44,250per acreCut, grub, chip, haul-off
Weed abatement and brush cutting (fire clearance)$1,775 – $2,100per acreCut, rake, haul green waste
Tree removal within a clearing or demolition scope, trunk up to 6 in.$1,625 – $1,925eachCut, chip, haul-off
Tree removal within a clearing or demolition scope, trunk 6 to 12 in.$2,400 – $2,875eachCut, chip, haul-off
Tree removal within a clearing or demolition scope, trunk 12 to 24 in.$3,200 – $3,825eachCut, chip, haul-off
Tree removal within a clearing or demolition scope, trunk 24 to 36 in.$4,800 – $5,725eachCut, chip, haul-off
Tree removal within a clearing or demolition scope, trunk 36 to 48 in.$6,375 – $7,625eachCut, chip, haul-off
Stump grinding within a clearing scope, trunk up to 24 in.$615 – $735eachGrind below grade
Temporary construction fence, 6 ft chain link, up to 6 months$21 – $25per linear footPanels, stands, install and removal
Silt fence, 3 ft high$9.25 – $11.25per linear footInstall and remove
Fiber rolls (wattles), 9 in.$17.00 – $20.50per linear footInstall and remove
Stabilized construction entrance (rock)$12.50 – $14.75per square footRock pad install and removal
Storm drain inlet protection$180 – $220eachInstall and remove

Hydroseeding and irrigation

ItemPriceUnitIncludes
Hydroseeding (seed, fiber mulch, tackifier)$12,000 – $18,500per acreSeed mix, fiber mulch and tackifier sprayed on prepared soil
Hydroseeding with bonded fiber matrix (slopes)$14,000 – $21,250per acreSeed plus bonded fiber matrix for slope erosion control
Irrigation system installed (Rain Bird or equivalent)$1.85 – $2.90per square foot of irrigated areaLayout, trenching, PVC mains and laterals, valves, spray/rotor heads or drip, smart controller, testing; backfill and cleanup
Irrigation, commercial and large open turf on rotors (1 acre or more)$1.35 – $1.85per square foot of irrigated areaRotor zones on open turf: layout, trenching, PVC mains and laterals, valves, rotors, smart controller, testing

Asbestos abatement

All asbestos abatement, whatever the size, is performed by a Cal/OSHA-registered asbestos abatement contractor under subcontract to SoCal Removal. The minimum is $1,950 per job.

ItemPriceUnitIncludes
Popcorn ceiling asbestos removal$9.50 – $12.75per square foot of ceilingContainment, removal, disposal, manifest
Asbestos floor tile and black mastic removal$17 – $23.50per square footContainment, removal, disposal, manifest
Asbestos drywall and joint compound removal$24.50 – $30.50per square foot of surfaceContainment, removal, disposal, manifest
Asbestos plaster or stucco removal$53 – $66per square foot of surfaceContainment, removal, disposal, manifest
Asbestos duct removal and disposal, round duct up to 6 in. diameter$84 – $105per linear footDuct, wrap, tape and boots; bagging and disposal
Asbestos duct removal and disposal, round duct 6 to 12 in. diameter$100 – $125per linear footDuct, wrap, tape and boots; bagging and disposal
Transite flue, water-heater vent or furnace-closet asbestos removal (HVAC contractor removes the furnace)$1,950 – $4,475per homeTransite flue, closet wrap and debris
Bathroom tub surround: asbestos tile, setting material and drywall on three walls (under 100 SF)$1,950 – $3,800per bathroomContainment, removal, disposal, waste manifest
Small asbestos jobs (closet, duct mastic, drywall cuts)$1,950 – $3,800per visitContainment, removal, disposal, waste manifest

Lead paint removal

ItemPriceUnitIncludes
Lead-based paint removal$15.75 – $22.50per square foot of painted surfaceContainment, removal, cleanup, disposal
Lead paint chip sample (third-party consultant, accredited lab)$95 – $120per sampleCollection, lab analysis, results
Lead dust wipe sample (third-party consultant, accredited lab)$95 – $120per sampleCollection, lab analysis, results

Tanks and hazardous materials

ItemPriceUnitIncludes
Underground storage tank (UST) removal, steel fuel or holding tank, up to 15,000 gallons$1.85 – $2.65per gallon of capacityCleaning and rinsate disposal, excavation to expose, removal, cutting, transport and recycling, native backfill
Above-grade tank removal, steel fuel or holding tank, up to 15,000 gallons$1.85 – $2.65per gallon of capacityCleaning and rinsate disposal, disconnection, cutting, transport and recycling
Petroleum-contaminated soil, excavation$25 – $30per tonDig and stockpile on liner
Petroleum-contaminated soil, loading$14 – $17per tonLoad for transport
Petroleum-contaminated soil, thermal treatment$90 – $110per tonNon-hazardous soil, heated at a permitted facility to burn off the hydrocarbons; billed by scale weight, trucking priced by distance

Hauling and disposal

ItemPriceUnitIncludes
Construction and demolition debris removal (we load)$135 – $160per cubic yardLabor, loading, hauling, disposal
Clean concrete recycling fee, no rebar$24.50 – $30.50per cubic yardRecycler fee only; loading and trucking extra
Concrete recycling fee, with rebar$37 – $45.50per cubic yardRecycler fee only; loading and trucking extra

Testing

ItemPriceUnitIncludes
Asbestos bulk sample, PLM, standard turnaround$120 – $145per sampleCollection by an independent CAC or CSST, accredited-lab analysis, signed report
Asbestos bulk sample, PLM, next day$145 – $175per sampleCollection by an independent CAC or CSST, accredited-lab analysis, signed report
Asbestos bulk sample, PLM, same day$220 – $280per sampleCollection by an independent CAC or CSST, accredited-lab analysis, signed report
Asbestos point count, PLM 400-point (sample under 10%)$160 – $205per sampleRe-analysis at the same accredited lab, updated signed report
Asbestos air sample, PCM$74 – $95per sampleCollection by an independent CAC or CSST, accredited-lab analysis, signed report
Asbestos clearance air sample, TEM (AHERA)$495 – $615per sampleCollection by an independent CAC or CSST, accredited-lab analysis, signed report
Lead paint chip sample$95 – $120per sampleCollection by an independent CDPH-certified lead inspector or sampling technician, accredited-lab analysis, signed report
Lead dust wipe sample$95 – $120per sampleCollection by an independent CDPH-certified lead inspector or sampling technician, accredited-lab analysis, signed report

Drywall and patch-back

ItemPriceUnitIncludes
Drywall replacement, hung, taped and textured$5.25 – $7per square footBoard, tape, texture
Interior painting, walls and ceilings$3.70 – $4.75per square foot of surfacePrep, primer, two coats
Concrete slab replacement, 4 in.$15.75 – $20per square footBase prep, forms, concrete, finish
Asphalt patch-back, 4 in.$11.25 – $13.50per square footSaw cut, base prep, tack, hot mix

Waterproofing

ItemPriceUnitIncludes
Below-grade and wall waterproofing, fluid-applied membrane$10.50 – $13.75per square footSurface prep, primer, membrane
Below-grade waterproofing system, specified (90-mil membrane, epoxy primer, drainage panel, manufacturer warranty)$15.75 – $21per square footSurface prep, 2-coat epoxy primer, detailing, 90-mil membrane, drainage panel, manufacturer inspections and warranty
Penetrating concrete or masonry sealer$1.85 – $2.65per square footCleaning, sealer application

Minimum charges

Job typeMinimum
Asbestos or lead job$1,950 per job
Demolition, concrete cutting, site preparation, hauling, restoration or waterproofing job$3,750 per job
Tank removal$5,600 per tank, one removal mobilization
Additional tank, same site and mobilization$2,800 per tank
Tank removal return trip (remobilization)$1,950 per trip
Lab-results testing visit (asbestos or lead)$475 per visit
Rule 1403 asbestos survey (CAC-signed report)$1,000 per building

Permit or notice needed?

WorkPermit or notice usually needed
House or structure demolitionCity demolition permit and an air-district asbestos notification, even when no asbestos is found.
Interior demolitionUsually covered by the project’s building permit, plus an asbestos survey
Asbestos abatementAir-district notification and Cal/OSHA notice on jobs of 100 SF or more.
Lead abatementCDPH notification for abatement projects
Pool removalCity demolition permit, with inspections
Tank removalCounty (CUPA) or fire department removal permit, with an inspector on site
Excavation and gradingCity grading permit above the city’s threshold; Cal/OSHA permit for trenches 5 ft or deeper that workers enter; DigAlert ticket
Concrete and asphalt removalUsually none on private property; encroachment permit in the public right-of-way
HaulingEncroachment permit for a bin in the street; recycling plan in many cities
Land clearingGrading or tree permits in some cities; usually none for weed abatement
Hydroseed, irrigation, waterproofing, patch-backUsually none, or covered by the project’s building permit

Requirements vary by city and county. Permit fees are not included; we pull or coordinate the permits our work needs, billed at cost plus administrative time. See demolition permit and AQMD fees.

What if the site doesn’t match the plan?

Worked examples using these unit prices, with what else to budget for: permits, inspections and standby, testing, manifests, coordination and administrative time. Each example is an illustration under its stated assumptions, not a quote.

What if…Example budget, high endWorked example
The asbestos survey finds popcorn ceiling in a house being demolishedUp to $63,550 for 1,500 SFDemolition cost
The slab and foundation come out tooUp to $76,500 for 1,500 SFDemolition cost
Old flooring tests positive for asbestosUp to $18,800 for 800 SF, plus testingFloor tile and mastic cost
The slab is thicker than the drawings showUp to $57,000 for 3,000 SF at 8 in.Concrete and asphalt cost
The job is just under 5,000 SFNever billed above the 5,000 SF priceConcrete and asphalt cost
The asbestos is only a few square feet$1,950 job minimumAsbestos removal cost
Grading uncovers an unknown buried tank$5,600 minimum, plus agency items at costTank removal cost
Export soil turns out to be contaminatedUp to about $157 per ton before truckingExcavation and grading cost

Using these prices

Use these ranges as budget unit prices for early estimates, alternates and added or deleted quantities. Contract unit prices are set in the proposal or bid, and large commercial and public projects are priced from plans or bid documents, often with volume pricing. Proposals break into a schedule of values for monthly pay applications. Cost terms glossary

Request a project review or call (949) 446-0000

Disclaimer: a guide, not a quote.

These prices are a guide for budgeting, not a quote. They are our 2026 price ranges for common projects in Southern California. Your written price depends on the site, access, quantities, the materials found, the schedule and the documents you provide, and it can come in above or below these ranges; the written proposal governs.

Permits, inspections and other government fees vary from city to city and county to county and are not included. Neither are plan preparation, engineering, utility planning, agency submittals and coordination, inspector standby, return trips or administrative time, other than the asbestos air-district notice we prepare and file. Testing is priced on the testing page. Worked examples illustrate their stated assumptions and are not quotes. When a project needs any of these, they’re listed in the written proposal.

A written proposal follows a site walk or a review of your plans, reports and photos.