Lead-Related Removal & Selective Demolition Lantern Village, Dana Point, CA
Dana Point Lead-Related Tile and Wall Removal
SoCal Removal held the customer-facing contract and a qualified abatement subcontractor for designated tile, floor-trim, and painted-wall removal after a limited renovation-area survey identified lead-based coatings on selected components.

- Location
- Lantern Village, Dana Point, CA
- Survey
- Limited asbestos and lead evaluation
- Planned tile scope
- Approx. 800 SF
- Planned wall scope
- Approx. 400 SF
- Delivery
- SoCal prime with qualified subcontractor
- Documented media
- 14 photographs
Verified Project Record
Defined work and responsibility lines
Project records identify tested materials, planned work limits, contractor roles, and specified cleaning controls.
Documented contractor scope
- Review the consultant-prepared limited renovation-area survey before defining disturbance limits.
- Subcontract removal of approximately 800 square feet of designated ceramic tile and floor trim across the identified levels.
- Subcontract removal of approximately 400 square feet of identified lead-painted plaster and drywall in selected second-floor rooms.
- Use temporary barriers, HEPA vacuuming, wet wiping, and crawlspace ground protection where the project documents required them.
- Keep shower mortar, concrete removal, structural work, concealed conditions, and restoration outside the documented removal scope unless separately authorized.
Prime-contractor control with defined specialty work
Abajian Enterprise dba SoCal Removal held the customer-facing contract and the project. Coronel Demolition, Inc. performed the specialty field work under SoCal Removal’s subcontract work order. The environmental survey and laboratory analysis were prepared by independent qualified parties.
Original Project Photography
What the field record shows
Project photographs show original finishes, temporary protection, contained work areas, and selected assemblies opened during removal.

Project setting

Laundry and kitchen floor

Galley kitchen floor

Entry floor transition

Interior tile steps

Fireplace finish

Balcony tile

Interior work enclosure

Upstairs access barrier

Bathroom opened to framing

Room opened to framing
Discuss Your Scope
Planning lead-related removal before renovation?
Send the available plans, surveys, photographs, schedule requirements, and site information so our team can evaluate the contractor scope and identify missing prerequisites.